| Board
of Park Commissioners |
|||||||||
![]() |
Timeline February 5 - Lombard Park District residents pass a referendum that supports the construction of a new community pool. February 12 - The Board of Park Commissioners recommit their preference for conceptual plan 3.2 (see left). February 19 - LPD staff meet with a construction manager and architect to begin establishing a timeline, consider alternatives for project including sand play area, utilities and demolation preparation. February 26 - FGM Architects presented information on development of the Lombard community pool. Demolition and separating the utilities would be phase one and phase two would be construction. A Village zoning, building and engineering meeting took place to discuss a public hearing. Additionally, FGM Architects met with staff for a few changes to the pool that they will bring back to the board. Phase One demolition is expected to begin mid-June.
|
||||||||
|
|||||||||